Thursday, May 8, 2014

Monday inspections, Tuesday through Thursday concrete!!

May 7th

Tom and Lee La Duke have been hard at work and have finished back filling the foundation with rock and then DG (decomposed Granite). Mike Mark (our plumber, framer, and who know what else we will hire him to do) made the changes we decided on in our master bath and second bath. The inspector is scheduled to come out on Monday and then we will be pouring concrete Tuesday through Thursday!

This shot is from the living room looking back through the kitchen (the two black pipes on the right are in the kitchen island)

This is looking at the kitchen and dining room areas

This shot is looking at the front door. The door will be on the left side of the wall we can see in the foreground.

This is the stair area and the garage.

This is the garage door and what will eventually be our driveway. looks like we will need a lot of fill to bring up the driveway to the level of the garage. So glad I didn't spend a lot of time moving rock for our driveway! I was planning on doing just that and K convinced me that it would be better to wait and see what would need to be moved after the foundation is poured. So glad she is so smart! :)

This area is just out side the kitchen and dinning room. This will probably be where we spend most of our time outside while our kids are young. We are planning on installing synthetic turf. It is so nice to not have to cut or water a "play area" that looks and feels like grass. :)

This is the view from the kitchen sink looking through the dining area. The rocks will be incorporated into a patio as the base. 